Trace GC Preventive Maintenance Intervals
Topic
Here is the maintenance schedule for the Trace GC.
Environment
- Trace GC 1300 Series
- Trace GC 1600 Series
Steps/Procedure
- Clean exterior surfaces using lint-free cloth and/or soapy water — Quarterly or as needed.
- Leak checks — Weekly.
- Helium filters or gas scrubbers — Checked quarterly and replace yearly.
- Injector maintenance:
- Change Septa.
- Change Liner.
- Replace seals/O-rings.
- Injection maintenance is sample dependent. Dirty matrices might require more inlet cleaning.
- After every 100 injections.
- Depending on instrument performance. Carryover and syringe contamination could contribute to a dirty liner.
- Typically done when there are leaks.
- Always utilize the leak check function after column installation or trimming.
- Column maintenance:
- Columns can last a long-time if properly taken care of.
- Consider using guard columns or backflush connections to minimize downtimes.
- Check for leaks using a leak detector or through the mass spectrometer (if connected).
- Do this on a weekly basis.
Additional Information
- The GC oven itself requires little to no maintenance.
- Injectors or detectors require the most maintenance.
- This e-learning is going to focus on just injector maintenance due to the coupling of the GC to the ISQ.
- Column maintenance is another critical routine maintenance procedure.
- Column maintenance is determined when instrument performance deteriorates, and troubleshooting indicates that a replacement or trimming is required.